Namibia's new container terminal 76 pct complete

Source: Xinhua| 2018-02-01 23:29:40|Editor: yan
Video PlayerClose

WINDHOEK, Feb. 1 (Xinhua) -- Namibia's 344 million U.S. dollars container terminal currently under construction in its coastal town of Walvis Bay is 76 percent complete, the Namibian Port Authority (Namport) said Thursday.

According to a statement issued by Namport, the contract is on schedule for completion of most of the works at the end of 2018 with minor works to be completed early 2019.

One of the major components of the projects is the commissioning of four new Ship Container Cranes (STS), making it the first time that these cranes will be deployed in the port of Walvis Bay.

Namport has to date made use of mobile cranes to load and offload containers from vessels.

The 4 STS cranes are expected to arrive from China on February 10, 2018.

The project which commenced in May 2014 with the contractor being China Harbor Engineering Company Limited will have a throughput capacity of 750,000 TEUs (twenty foot equivalent units) per annum.

The new port will also be connected to the existing port's road and rail networks as well as communication systems.